Our Work: Modern Master Bath Remodel

Project Description

This project was a complete master bath, mater closet and master bedroom remodel. We completly relocated the master closets closer to the master bath and by moving the closets, we were able to add a french door and windows overlooking the patio and back yard. We also had to remove the existing concrete slab that th original bathroom sat on and pour a new foundation. we relocate all the drain lines, re-plumbed the entire home and added 2 tankless water heaters. This project had many custom cabinets, vanity and built-ins. Everything in this project was special order and top of the line.

}

Duration

120 days

Cost

96K

Designed By

Everhart Design Team